Project control tower
Attention & next actions
Quarterly office refurbishment programme · 0 open records
No open records
Missing records do not establish readiness.
Approved budget
£2.4m
Forecast final cost
£2.37m
Forecast variance
£30k
Delivery progress
56%
Project scope
Q4 programme covering 80 office units across the London portfolio. Detailed unit schedules planned in phase four.
Project ownerSarah Bennett
Delivery stageConstruction
Start date01 Oct 2026
Target completion31 Dec 2026