Project control tower
Attention & next actions
Westbrook House refurbishment · 7 open records
Approved budget
£1.2m
Forecast final cost
£1.26m
Forecast variance
-£62k
Delivery progress
64%
Project scope
Commercial refurbishment of reception, floors 2–4 and associated building services. Occupied ground floor retained; tenant access maintained.
Project ownerJames Mitchell
Delivery stageConstruction
Start date03 Aug 2026
Target completion18 Dec 2026
Delivery actions
RFI-024 · Ceiling coordination response
Design response is blocking first-floor ceiling closure.
James Mitchell · Due 17 Nov 2026Reception finish approval
Client decision required before placing the stone order.
Sarah Bennett · Due 16 Nov 2026First-floor ceiling closure
Blocked by RFI-024
James Mitchell · Due 24 Nov 2026Complete reception finishes
Awaiting client finish approval
James Mitchell · Due 04 Dec 2026M&E commissioning
Commissioning plan under review
Tom Harris · Due 11 Dec 2026Practical completion review
Formal certification requires appointed authority
James Mitchell · Due 18 Dec 2026